Add Milestones/Steps
Create milestones and steps for work packages that use the Milestones or Steps progress technique.
To add milestones or steps to a work package, complete the following steps:
- Display the Project view, select a work package in the Spreadsheet pane, and select the Milestones/Steps tab.
-
To add milestone, take one of the following actions:
- In the Milestone/Step group on the Project Edit tab, click .
- Right-click the Milestones/Steps grid and select Add Milestone on the shortcut menu.
-
To add a step, take one of the following actions:
- In the Milestone/Step group on the Project Edit tab, click Step.
- Right-click the Milestones/Steps grid and select Step on the shortcut menu.
Cobra adds a row to the Milestones/Steps grid. Use this row to add information required for a milestone or step, such as description, dates, and weight factor.
You can add milestones to a work package if that work package uses the Milestones progress technique. You can add steps to a work package if that work package uses the Steps progress technique. You cannot modify information about a milestone or step if the work package has a status of Completed.