Add Time Phased Data

Use this procedure to add time phased data at the work package (WP) and control account (CA) level for manual entry of costs using the Costs Tab of the Change Details form.

Before you begin, see Rules for Editing Change Details Data.

To add time phased data, complete the following steps:

  1. On the Navigation menu, click Administration » Workflows » Change Management.

  2. In the List View, select the change request.

  3. On the General tab of the Change Request form, click the Change Details button.

  4. On the Change Details form, select a work package or a control account if the class level is the forecast level.

  5. On the Costs Tab, click Insert.

  6. On the Add Resource Assignment dialog box, enter all applicable details. This populates the Time Phased_Grid_Columns_and_Rows.

  7. Click Save.