Move a Task on Phase to Scrum Sprint (from the Phase Settings Screen)
Use the Tasks submodule to move a task on phase to scrum sprint.
To use Tasks, you must have access to Jobs as defined in User Access Rights under Settings.
To move a task on phase to scrum sprint:
-
On the main toolbar, click
Jobs
.
- In the left pane of the Jobs page, click Jobs List and highlight the job containing the tasks that you want to move.
- In the left pane of the Jobs page, click Tasks.
- On the Tasks page, click the Tasks tab.
- On the grid toolbar, click the Gantt view.
-
In the grid, highlight the phase containing the tasks that you want to move and click
Phase Settings
on the tab toolbar.
-
On the toolbar of the Phase Settings screen, click
Move a Task on Phase to Scrum Sprint
.
- In the Move Tasks dialog box, select an option and click OK.
Parent Topic: Tasks Tab